Strawberry Lane, Strawberry Court & Peach Circle


Project Overview

Construction on Strawberry Lane includes a 26-foot roadway width, a curb and gutter on both sides of the road, and the addition of watermains and fire hydrants, providing residents with an opportunity to connect to city water and to provide fire protection to homes along the corridor. A 6-foot sidewalk was also installed. All major construction has been completed for 2023.

Topsoil touchups, remaining irrigation repair, landscape restoration, and remaining boulevard cleanup items will take place in the Spring of 2024. Detailed updates will be released when the crews are scheduled to be back on-site next Spring.

Strawberry Lane Watermain Installation
Residents of Strawberry Court, Strawberry Lane and Peach Circle will be offered the ability to connect to city water if desired upon completion of the watermain installation construction project in 2023. Please contact the city at 952.960.7900 for additional information or to be added to the interest list.


Project Schedule
Strawberry Lane Progress Bar -11.22.23

Frequently Asked Questions
Answers to questions about connecting to city water, trees, roadway and sidewalk, and more can be found on the Strawberry Lane FAQ page. 


Project Documents
2022

Draft Reconstruction Plan 
Strawberry Lane Reconstruction & Drainage Project (one-pager)
Strawberry Lane Tree Inventory Plan 
Strawberry Lane & Smithtown Pond Trail Tree Inventory

2021
Feasibility Study and Presentation
Strawberry Lane Comparison Map and slides
Strawberry Lane Open House Presentation 


Project Contact

Andrew Budde, City Engineer, 952.960.7900


Updates
Please make sure you are on the email list for the Strawberry Lane  project to receive project updates and alerts. Sign up online, or contact City Hall to be added to the list. Below updates include summaries and links to these emails. These updates will be archived in early 2024.

11/22/23 - Seeding will be taking place on Monday. No work scheduled until Spring 2024

11/15/23 - Topsoil restoration, driveway prepping & boulevard cleanup will continue next week

11/9/23 - Driveway prep and paving, topsoil, and restoration work - Nov 9 thru 17

10/31/2023 - Paving scheduled Thurs and Fri this week due to the weather we had this morning

10/20/23 - Schedule Adjustment: Crews to pour concrete sidewalk

10/18/23 - Paving scheduled to begin TUESDAY, October 24

10/16/23 - Concrete Construction Work - Week of October 16th

10/6/23 - Due to today's rain event, Concrete crews have been pushed to begin pouring Curb and Gutter on Tuesday October 10th.

10/4/23 - Modified schedule updates, roadway mainline paving, mailboxes

9/29/23 - No construction today; IMPORTANT updates for residents living on south end of Strawberry Ln

9/28/23 - Crews will be onsite until 8:30pm tonight

9/27/23 - Sept 27-Oct 6 Project Schedule; IMPORTANT parking information during Concrete Curb & Gutter Installation

9/21/23 - Sept 25-29 Project Schedule; Concrete Curb & Gutter Schedule Modification

9/13/2023 - Schedule Updates & Projected Completion Dates

9/7/2023 - Parking details during road construction next week

8/31/2023 - Important parking information, water outage for some late next week

8/24/23 - Intersection at 62nd closed, storm sewer & watermain to continue, roadway construction begins next week

8/17/23 - Shorewood Oaks Dr intersection will be closed Aug 18

8/11/23 - Sewer construction continues, watermain installation begins next week, roadway excavation rescheduled

8/4/23 - Sewer construction, driveway removals to continue, temp water outage

7/26/23 - Gravel & Driveway Removals begin July 27

7/19/23 - Temporary Water Outage along Alexander Lane on July 20th

7/13/2023 - July 13 to July 21 Project Schedule

7/7/2023 - July 10 to 14 Project Schedule

6/29/2023 - Strawberry Lane closed to thru traffic starting June 30th

6/26/23 - Temporary lane closure on Smithtown Road - Wednesday 6/28

6/21/23 - Roadway Construction Start Up Week of June 26th

6/15/2023 - Temporary mailboxes are planned to be installed

6/7/2023 - Private Utility Work is Wrapping Up

5/26/2023 - • Silt fence and erosion control items will be installed today

5/18/2023

5/12/2023 - Storm Sewer Construction Startup on 5/15/23

5/9/2023

5/5/2023

4/27/2023

4/17/2023

3/30/2023

3/8/2023

2/23/2023

11/23/2022

10/31/2022

10/22/2022

2/28/2022 - City Council Meeting

2/14/2022 - City Council Meeting

11/10/2021 - Public Information Open House

7/26/2021 - Council Meeting

6/22/2021 - Neighborhood Meeting

6/7/2021 - Letter

4/26/2021 - Feasibility Study and Presentation

3/11/2021 - Public Meeting